Federal appeals court orders halt to work on Atlantic Coast Pipeline

  • Government
  • Judicial
  • Statute
  • Energy

The Washington Post – A federal appeals court has ordered a halt to construction of Dominion Energy’s Atlantic Coast Pipeline, finding that restrictions against harming wildlife are inadequate for the controversial 600-mile natural gas project.

Three judges of the U.S. Court of Appeals for the Fourth Circuit said in a ruling issued late Tuesday that the U.S. Fish and Wildlife Service had failed to set clear limits for impact on threatened or endangered species.

The judges said that “the limits set by the agency are so indeterminate that they undermine … the enforcement and monitoring function under the Endangered Species Act.”

The case was brought against the pipeline by the Southern Environmental Law Center on behalf of the Sierra Club, Defenders of Wildlife and the Virginia Wilderness Committee.

Read more at The Washington Post.